Skip to main content

Purchase Order Approval

Set value based approvals on Purchase Orders

Niall Brennan avatar
Written by Niall Brennan
Updated this week

Where a user creates a purchase order and requires approval from one person when over a certain value. This means the Purchase order email will not be sent the supplier until approval is given.

eg: Joe Bloggs requires approval from the Project Owner when raising Purchase Orders over the value of $ 100

Where a user creates a purchase order and requires approval from two people when over a certain value. This means the Purchase order email will not be sent to the supplier until approval is given.

eg: Joe Bloggs requires approval from the Project Owner & Director when raising Purchase Orders. Purchase Orders over $100 will be approved by the Project Owner but when Purchase Orders are raised over $10,000 this will require a second approval by the Director.

To Create a One Step Approval

1. Go To Settings - Workflows

2. Create a new P/O Approval One Step

3. Fill Out all required fields

  • Name : Give the Approval a descriptive name

  • Subtotal : Set a value where this approval kicks in
    Note if every P/O needs approval set value to 0

  • Requester : Set the person who requires approval

  • The Approvers : Set the people / person who can approve

    Note : if setting the approver to be the project owner, please ensure a project owner exists, if not the approval will be automatically given


To Create a Two Step Approval


1. Go to Settings & Workflows

2. Create a new P/O Approval Two Step

3. Fill Out all required fields

  • Name : Give the Approval a descriptive name

  • Step 1 : Subtotal Amount : Set a value where this approval kicks in
    Note if every P/O needs approval set value to 0

  • Requester : Set the person who requires approval

  • Step 1 Approver(s) : Set the people / person who can approve the first step.

    Note : if setting the approver to be the project owner, please ensure a project owner exists, if not the approval will be automatically moved to step 2

  • Step 2 : Subtotal Amount : Set a value where the 2nd approval kicks in
    Note if every P/O needs two approvals set the value the same as the Step 1 amount.

  • Step 2 Approver(s) : Set the people / person who can approve the second step.

    Note : The first step must be approved before it is passed to the second step

    If setting the approver to be the project owner for step 2, please ensure a project owner exists, if not the approval will be automatically given

Did this answer your question?